Home > News > Executing the Complete Power Generation Project
Executing the Complete Power Generation Project. Author: mbncom |
|
In today’s climate of advanced environmental regulations and greater public awareness (or sometimes fear) of energy issues, the evaluation, planning, and permitting of new power plants are critical issues. For a developer today to be successful, they must select the best technology and site, receive the required permits and construct the plant in a timely and cost-effective manner. This article examines the most important issues of this process, with a particular focus on the most popular installations in the U.S., combined-cycle power generation plants. However, many of the topics apply to other methods of power generation including coal, stand-alone combustion turbines, biomass plants and others.
Steps 1 and 2– Site and Technology Selection Many variables must be clarified/determined during this phase of project development. These items include:
Some of these variables are easier to identify than others, but all need to be addressed very early in the project development cycle. The lack of timely decisions can significantly impact the overall project schedule. Owners today are being challenged with permitting and interconnection agreements that may take in excess of 12 months to complete. Lead times for major equipment acquisition are another schedule driver and will become a greater challenge as the global market for these products continues to grow. To help minimize the impact of equipment acquisition, a limited engineering release is necessary to begin procurement and preliminary design. Developers need a thorough understanding of the selected site prior to acquiring bids from engineering and construction firms, as this will greatly influence the final cost of the project. While much data exists in the public domain regarding subsurface conditions for many states and counties across the country, the data is often not specific enough to finalize costs and schedules. Often, a site investigation with only a handful of borings can give much insight, but a detailed study should be completed before design commencement or site activities.
With regard to equipment selection, a number of reputable and experienced vendors are available both nationally and globally to supply the major equipment plus the auxiliaries. Of course, the key selections include the combustion turbines, HRSGs, and steam turbine. However, auxiliary systems should not be overlooked by excessive focus on the major equipment. Important auxiliaries include transformers, makeup and cooling water equipment, auxiliary boilers, and instrumentation and control systems, to name several. As the decision is made regarding the primary technology, thereupon comes development of heat and water balances. Modern programs incorporate specific data from the equipment chosen and will produce accurate calculations for many parameters including combustion turbine output, heat rate, steam production in the HRSGs, cooling tower performance and circulating water flow rate, among others. This data in turn allows refined calculations of water balances. Precision is paramount, as the water balance determines the required capacity of makeup water, and at times cooling water, treatment equipment. Undersizing of such equipment can lead to severe operating problems at and after startup, while oversizing adds significant cost to the system and may also result in poor performance. Another factor of importance is that a poor water balance can lead to installation of piping that is either too small or large for the application. Excel or a similar spreadsheet program is an excellent tool for preparing water balances, as water flow rates and usage can easily be calculated for any variety of conditions.
Once equipment selection has been finalized, the focus shifts to equipment layout. Some sites offer plenty of space for combustion turbine and auxiliary systems placement, but others may be very tightly constrained. One of the most significant factors for overall plant cost is quantities of commodities. Regardless of the space available, proper effort is needed to optimize the plant layout and in turn accurately calculate quantities and simplify construction. Factors that impact quantities include: piping and wiring locations and run lengths, steam turbine location, switchyard location, water treatment building placement, cooling tower location and many others. It is important as a developer or utility to write the RFP in a manner that gives the EPC contractor flexibility regarding the plant layout. This is possible while still maintaining pre-established emission points included in air permit applications. As the equipment is being laid out two-dimensionally, designers also construct the model in 3D, which allows a much better analysis of pipe rack, cable tray and other overhead equipment locations. Development of the equipment arrangement expediently and with precision is also important for planning of of underground piping and electrical supplies. These need to be installed accurately upon the first attempt, as otherwise considerable time and effort may be expended in rerouting piping and cables after the fact.
All of these decisions factor into final technology selection. Besides power requirements, important aspects of combustion turbine selection include:
Go back |